Presence Center for Advanced Care


Presence Center for Advanced Care

We're building the future of health care right next door.

We strive to be a good neighbor. Please contact us with any questions, concerns or suggestions.

Emergency Construction Hotline: 847.214.6743
Security Hotline: 773.665.3168
Construction email: sjhconstruction@presencehealth.org
For your convenience, parking is being made available for you at Presence Saint Joseph Hospital during construction. Learn more.

Watch our progress.

Click on the image to the right and our live construction camera will show you how the Presence Center for Advanced Care is taking shape!

 

 

 

Construction Updates

 

About Safety Lighting

The interior lights within the building are required by OSHA and the City of Chicago building code during building construction. They are there to ensure that first responders would be able to see where they are going in the event of an emergency. All buildings in Chicago that are under construction have this clearly visible internal lighting during construction.

 

 

 Week of 04.06.15

  • MEP above ceiling work continues on the 1st floor
  • Continue partitions on the Ground Floor
  • Continue painting on the 1st floor
  • Continue ceiling work on the 1st floor
  • Continue millwork on the 1st floor
  • Continue windows on the north, south, and east elevations
  • Continue partitions on the 5th and 6th floor
  • Begin framing the 9th floor
  • Continue layout and top track on the 6th floor
  • Continue MEP above ceiling work on the 5th floor and 6th floor
  • Continue masonry on the garage floors
  • Continue structural stud framing
  • Continue penthouse wall framing and sheathing
  • Continue installing exterior louvers
  • Continue work in the mechanical penthouse
  • Continue elevator installation

  •  

     

Week of 03.30.15

  • MEP above ceiling work continues on the 1st floor
  • Continue partitions on the Ground Floor
  • Continue painting on the 1st floor
  • Continue ceiling work on the 1st floor
  • Continue millwork on the 1st floor
  • Continue windows on the north, south, and east elevations
  • Continue partitions on the 5th and 6th floor
  • Begin framing the 8th floor
  • Continue layout and top track on the 6th floor
  • Continue MEP above ceiling work on the 5th floor and 6th floor
  • Continue masonry on the garage floors
  • Continue structural stud framing
  • Continue penthouse wall framing and sheathing
  • Continue installing exterior louvers
  • Continue work in the mechanical penthouse
  • Continue elevator installation
  • Continue thermal spray in the penthouse exterior walls

Week of 03.23.15

  • MEP above ceiling work continues on the 1st floor
  • Continue partitions on the Ground Floor
  • Continue painting on the 1st floor
  • Continue ceiling work on the 1st floor
  • Continue millwork on the 1st floor
  • Continue windows on the north, south, and east elevations
  • Continue partitions on the 5th and 6th floor
  • Continue layout and top track on the 6th floor
  • Continue MEP above ceiling work on the 5th floor and 6th floor
  • Begin framing the 7th floor
  • Continue masonry on the garage floors
  • Continue structural stud framing
  • Continue penthouse wall framing and sheathing
  • Continue roofing on the 6th floor roof
  • Continue installing exterior louvers
  • Continue work in the mechanical penthouse
  • Continue elevator installation
  • Begin thermal spray in the penthouse exterior walls
  • Dismantle Tower Crane

 

 

Week of 03.16.15

  • MEP above ceiling work continues on the 1st floor
  • Continue partitions on the Ground Floor
  • Continue painting on the 1st floor
  • Continue ceiling work on the 1st floor
  • Continue millwork on the 1st floor
  • Continue windows on the north, south, and east elevations
  • Continue partitions on the 5th and 6th floors
  • Continue layout and top track on the 6th floor
  • Continue MEP above ceiling work on the 5th floor and 6th floor
  • Continue masonry on the garage floors
  • Continue structural stud framing
  • Continue penthouse wall framing and sheathing
  • Continue roofing on the 7th floor roof
  • Begin roofing on the 6th floor roof
  • Complete penthouse spray on fire proofing
  • Continue installing exterior louvers
  • Begin mechanical work in the penthouse
  • Begin elevator installation
  • Begin thermal spray on the perimeter walls on 5

Week of 03.09.15

  • MEP above ceiling work continues on the 1st floor
  • Continue partitions on the Ground Floor
  • Continue painting on the 1st floor
  • Continue ceiling work on the 1st floor
  • Continue millwork on the 1st floor
  • Continue windows on the north, south, and east elevations
  • Install precast on the north elevation
  • Continue partitions on the 5th floor
  • Continue layout and top track on the 6th floor
  • Continue MEP above ceiling work on the 5th floor and 6th floor
  • Continue masonry on the garage floors
  • Continue structural stud framing
  • Continue elevator divider beams, stair beams, and light boom supports
  • Continue penthouse wall framing and sheathing
  • Complete penthouse roofing
  • Begin penthouse spray on fire proofing
  • Begin installing exterior louvers
  • Begin roofing on the 7th floor roof
  • Begin thermal spray on the perimeter walls on 6

 

Week of 02.16.15

  • MEP above ceiling work continues on the 1st floor
  • Continue partitions on the Ground Floor
  • Continue windows on the north, south, and east elevations
  • Install bridge roofing
  • Install precast on the north and south elevations
  • Continue layout and top track on the 5th floor and 6th floor
  • Continue MEP above ceiling work on the 5th floor and 6th floor
  • Continue masonry on the garage floors
  • Continue structural stud framing
  • Continue elevator divider beams, stair beams, and light boom supports
  • Com Ed energizes their vault
  • Continue penthouse wall framing
  • Begin roofing the bridge

 

Week of 02.23.15

  • MEP above ceiling work continues on the 1st floor
  • Continue partitions on the Ground Floor
  • Continue windows on the north, south, and east elevations
  • Install bridge roofing
  • Install precast on the north and south elevations
  • Continue layout and top track on the 5th floor and 6th floor
  • Continue MEP above ceiling work on the 5th floor and 6th floor 
  • Continue masonry on the garage floors
  • Continue structural stud framing
  • Continue elevator divider beams, stair beams, and light boom supports
  • Continue penthouse wall framing

Presence Center for Advanced Care site logistics plan with construction update

Presence Center for Advanced Care construction schedule

Call 877-RES-INFO for Nurse Advice, Doctor Referrals or Class Registration Monday - Friday 8 am to 8 pm • Weekends 8 am to 4pm

Special Features

  • Top cardiovascular hospital

    Recognized as a 2014 Top 50 Cardiovascular Hospital by Truven Health Analytics. Learn more.

  • Accreditation Earned

    Chicago Institute of Advanced Bariatrics earns national accreditation from the ACS.

  • Academic Center of Excellence

    Named an Academic Center of Excellence by the American Institute of Minimally Invasive Surgery. Learn more.

  • We need your voice!

    Our legislators are tackling issues that impact on our ability to live our mission. Learn more »

For Your Good Health

  • Stories of Patient Care

    Find out what our patients are saying about us here at Saint Joseph Hospital.

Saint Joseph Hospital has gone social